Capital Improvement Program

Project: Sweetwater Fire Station Project No: PB0533 Status: Complete Category: Public Building Improvements
Location: 1751 Grove Point Rd Start Year: 2011 End Year: 2018
Council District: 6 Project Manager: Elzie Kitchen| Leif Blomberg ekitchen@Savannahga.Gov; LBlomberg@savannahga.gov
Scope: New Construction to replace current modular building
Comments: 12/11/2020 8:47:49 PM:
Record drawings have been received from design consultant and will be reviewed. Project account will be closed out in 4th Quarter of 2020.

7/27/2020 8:08:58 PM:
Record drawings expected from design consultant in early August to be reviewed. Close-out activities are expected to be completed in 4th Quarter of 2020.

4/4/2020 10:49:39 PM:
Record documents will be completed and submitted for review in April. Close-out activities are expected to be completed in 2nd Quarter of 2020.

12/18/2019 4:37:00 PM:
Final warranty items are being addressed. Record documents will be completed and submitted for review in January. Close-out activities are expected to be completed in 1st Quarter of 2020.

10/3/2019 7:41:09 PM:
Warranty close-out walk-thru conducted on 9/17/2019. Record documents to be finalized. Miscellaneous close-out activities are expected to be completed by 12/31/2019.

7/2/2019 3:15:36 PM:
Contractor has received Final Acceptance letter and final payment. Record documents to be finalized. Miscellaneous close-out activities are pending and underway.

4/5/2019 2:47:45 PM:
Modification of retention pond has been completed. Site work and general contract close-outs are underway. Record documents are to be finalized.

1/2/2019 10:30:30 AM:
Construction is completed and the station is in operation. Modification of retention pond will completed as soon as weather allows. Project close-out is underway. Approval of contract change order is on the agenda for the January 17 City Council meeting.

10/5/2018 12:50:40 PM:
Savannah Fire and Capital Projects met with the Contractor and Architect for a Final Inspection on 1 October. Savannah Fire is expected to obtain the Certificate of Occupancy by 11 October with Savannah Fire moving in to provide service delivery from this station the week following. This Fire Station will house personnel, apparatus, and equipment for Engine company #15.

7/3/2018 3:56:50 PM:
Construction is funded, and in progress for this replacement Fire Station and is expected to be completed in 3rd quarter of 2018. Recent completed work includes: Storefront entrances installed 6/18/18, Electric power transferred from GA Power on 6/25, and Plumbing trim out began 6/22. This Fire Station will house personnel, apparatus, and equipment for Engine company #15.

4/5/2018 4:50:39 PM:
Construction is in progress for this replacement Fire Station and is expected to be completed in 3rd quarter of 2018. Interior stud framing will be completed by April 7th. Installation of roof finish panels and exterior stucco will start in April.

4/5/2018 4:50:39 PM:
Construction is in progress for this replacement Fire Station and is expected to be completed in 3rd quarter of 2018. Interior stud framing will be completed by April 7th. Installation of roof finish panels and exterior stucco will start in April.

12/22/2017 3:51:59 PM:
Construction is in progress and on schedule for this replacement Fire Station. Construction will be completed in 2018. This Fire Station will house personnel, apparatus, and equipment for Engine company #15.

9/29/2017 10:28:59 AM:
Construction is in progress with Dabbs-Williams (General Contractor). The site is cleared, and the building pad is being prepped.

6/28/2017 8:18:25 AM:
Savannah Fire hosted a Gound Breaking Ceremony on 5 May 2017. The Notice to Proceed is complete, and construction started 26 June 2017.

3/31/2017 12:08:38 PM:
Project expected to be put out for bid in January 2017.

Last Project Update: 12/11/2020 8:47:49 PM
Fund(s): Contrbtn Frm Generl Fnd | SPLOST VI(2015-2020
Project Financial Data Last Updated On: 9/30/2020 3:07:44 PM
Appropriated Budget To Date: Expenditures To Date: Open Purchase Orders: Project Balance:
$3,329,912.50 $3,329,912.50 $0.00 $0.00

SFES Prototype Fire Station
12/22/2017 3:51:59 PM