Project: Tompkins Center Renovation & Expansion Project No: PB0842 Status: Complete Category: Public Building Improvements
Location: 39th & Ogeechee Rd Start Year: 2013 End Year: 2017
Council District: 1 Project Manager: Barry Baker| Leif Blomberg BBaker@Savannahga.Gov; LBlomberg@savannahga.gov
Scope: Renovate and expand a portion of the existing building
Comments: 12/18/2019 4:38:17 PM:
Building record drawings were received from design consultant in November and consultant purchase order has been paid out. Site record drawings have been partially reviewed and will be finalized, along with other close-out documentation, in 1st quarter of 2020.

10/3/2019 7:43:49 PM:
Record drawings and other close-out documentation will be finalized and distributed, and consultant agreement will be paid out before the end of 2019.

7/2/2019 4:00:15 PM:
Consultant purchase order has been adjusted. Record drawings and other close-out documentation will be finalized and distributed, and consultant agreement will be paid out before the end of 2019.

4/5/2019 5:08:21 PM:
Close-out documentation and final consultant agreement amendment is in process. The project is expected to close out in the 2nd quarter of 2019.

1/2/2019 10:54:13 AM:
Close-out documentation and final consultant agreement amendment is in process. The project is expected to close out in the 2nd quarter of 2019.

10/4/2018 5:13:03 PM:
Close-out documentation and final consultant agreement amendment is in process. The project is expected to close out in the 4th quarter of 2018.

7/11/2018 5:41:19 PM:
Although the project is complete, staff has been working on final warranty items and a final consultant agreement amendment. The project should be completely closed out the 3rd quarter of 2018.

4/5/2018 5:03:46 PM:
The Tompkins Center renovation and addition project is completed and the center re-opened in May 2017. Close-out documentation is in progress. The one-year warranty inspection was conducted on March 30.

4/5/2018 5:03:46 PM:
The Tompkins Center renovation and addition project is completed and the center re-opened in May 2017. Close-out documentation is in progress. The one-year warranty inspection was conducted on March 30.

1/2/2018 3:15:47 PM:
Tompkins Center renovation and addition complete and the center re-opened in May 2017. Close-out documentation is in progress.

11/13/2017 5:28:01 PM:
Tompkins Center renovation and addition has been completed and the Center re-opened in May 2017 with daily operation.

7/19/2017 5:21:13 PM:
Renovations have been performed; Center is now open; Project is complete.

3/31/2017 12:08:38 PM:
Replacement of pre-existing sanitary sewer is underway and a storm line extension is being installed; gym floor finisher being applied which will complete construction of project.

Last Project Update: 12/18/2019 4:38:17 PM
Fund(s): Contrbtn Frm Generl Fnd | SPLOST VI(2015-2020) | SPLOST VI - District 1 Fund
Project Financial Data Last Updated On: 1/8/2020 1:13:09 PM
Appropriated Budget To Date: Expenditures To Date: Open Purchase Orders: Project Balance:
$3,070,715.32 $3,070,715.32 $0.00 $0.00


1/2/2018 3:15:47 PM