| Location:
1401 Mills B. Lane Blvd. |
Start Year:
NULL |
End Year:
Q3 2025 |
| Council District:
5 |
Project Manager:
Byron Stiles |
bstiles@savannahga.gov |
| Scope:
Installation of additional parking at the Liberty City Community Center. |
| Comments:
|
8/27/2025 2:43:09 PM: Additional parking spaces have been installed, and project is complete.
2/3/2025 9:18:27 AM: Construction contract approved by City Council in Q4 2024. Construction to begin in Q1 2025.
6/24/2024 4:11:57 PM: Design for the parking lot expansion is complete and approved. Construction to begin in Q3 barring any unforeseen issues.
12/6/2023 2:51:00 PM: Design is underway to increase the parking capacity by approximately 12 spaces. Design is expected to be completed in the late 4th quarter of 2023.
5/17/2023 11:37:04 AM: Project does not have enough funding to move forward.
|
| Last Project Update:
8/27/2025 2:43:13 PM |
| Fund(s):
NULL |
| Project Financial Data Last Updated On:
5/31/2025 12:00:00 AM |
| Appropriated Budget To Date:
|
Expenditures To Date:
|
Open Purchase Orders:
|
Project Balance:
|
|
$300,000.00 |
$132,488.59 |
$9,934.67 |
$157,576.74 |
|

9/19/2025 3:49:20 PM
|