Project: Summerside Sign Project No: PD0213 Status: Complete Category: Community Development Improvements
Location: Summerside Start Year: 2016 End Year: 2018
Council District: 5 Project Manager: Doug Patten DPatten@Savannahga.Gov
Scope: Construct a neighborhood entry sign for the Summerside Neighborhood
Comments: 12/14/2018 1:38:48 PM:
This project was completed was in March 2018.

10/9/2018 2:27:21 PM:
This project was completed was in March 2018.

6/26/2018 10:08:03 AM:
This project was completed was in March 2018.

3/22/2018 2:35:14 PM:
This project was completed was in March 2018.

3/22/2018 2:35:14 PM:
This project was completed was in March 2018.

12/14/2017 3:59:33 PM:
The sign was completed in August 2017. A change order was approved by City Council on November 21, 2017 to repair the planter. The planter work is expected to be completed by the end of the year. The contractor is Sign D'sign.

11/14/2017 11:14:11 AM:
Sign was completed in August 2017. Staff is currently looking at options to repair the planter. The project was awarded by City Council on March 30, 2017. The contractor was Sign D'sign.

3/31/2017 12:08:38 PM:
Project is out for bid

Last Project Update: 12/14/2018 1:39:02 PM
Fund(s): SPLOST VI - District 5 Fund
Project Financial Data Last Updated On: 1/28/2019 12:24:54 PM
Appropriated Budget To Date: Expenditures To Date: Open Purchase Orders: Project Balance:
$11,897.13 $11,897.13 $0.00 $0.00