Capital Improvement Program

Project: Cann Park Sign Project No: PD0312 Status: Complete Category: Community Development Improvements
Location: Cann/Jackson Park Start Year: 2017 End Year: 2017
Council District: 5 Project Manager: Douglas Patten DPatten@Savannahga.Gov
Scope: Construct a brick neighborhood entry sign for Cann/Jackon Park
Comments: 12/14/2017 4:02:19 PM:
This sign was completed in August 2017. The project was awarded by City Council on March 30, 2017. The contractor was Sign D'sign.

11/1/2017 3:09:38 PM:
This sign was completed in August 2017. The project was awarded by City Council on March 30, 2017. The contractor was Sign D'sign.

Last Project Update: 12/14/2017 4:02:30 PM
Fund(s): SPLOST VI - District 5 Fund
Project Financial Data Last Updated On: 2/1/2018 9:51:50 AM
Appropriated Budget To Date: Expenditures To Date: Open Purchase Orders: Project Balance:
$7,497.40 $7,497.40 $0.00 $0.00


12/14/2017 4:02:19 PM