Capital Improvement Program

Project: Edgemere/Sackville Recreation Project No: RE0129 Status: Complete Category: Parks and Recreation Improvements
Location: 56th-58th St. Start Year: 2015 End Year: 2019
Council District: 3 Project Manager: Kelly Ledbetter| Doug Patten KLedbetter@Savannahga.Gov; DPatten@Savannahga.gov
Scope: Develop a park/playground in the Edgemere/Sackville Neighborhood
Comments: 8/28/2023 11:51:50 AM:
Project is complete.

12/7/2020 3:54:29 PM:
Shelter installation has been completed.

7/27/2020 3:25:00 PM:
Installation of the shelter has started. It will be completed in Summer 2020.

3/16/2020 9:32:39 AM:
Shelter for the Edgemere/Sackville Park was submitted for permitting in March 2020. Once the permitting is complete, the shelter will be installed. Installation expected in the second quarter of 2020.

12/16/2019 10:21:51 AM:
The Edgemere/Sackville Park is complete and includes playground, walking trail with lights, park benches, chess/checker tables and landscaping and it is open to public for daily use and activities.

9/30/2019 3:50:59 PM:
The Edgemere/Sackville Park is complete and includes playground, walking trail with lights, park benches, chess/checker tables and landscaping and it is open to public for daily use and activities.

7/5/2019 8:38:07 AM:
The Edgemere/Sackville Park ribbon cutting was held in May and the Park is open and includes playground,walking trail, benches, chess/checker tables and landscaping. Installment of lighting for walking trail is expected to be completed in July.

4/5/2019 1:21:30 PM:
The playground was installed and opened to the public for use in January. Chess tables were ordered and expected to be delivered and installed in Mid May.

1/9/2019 3:08:00 PM:
Clearing and grading of site is underway and due to inclement weather at site, installation of playground is delayed to mid January.

10/2/2018 1:52:09 PM:
Playground installation planned for December and walking trail installation planned in January. Acquisition of adjacent properties to expand park space is completed.

7/6/2018 3:30:37 PM:
Edgemere/Sackville Park is under conceptual design to include property acquisition. Park development was delayed to allow for acquisition of adjacent properties and park expansion. Park will include playground, walking trail, benches, landscape and estimated completion in three to four months.

5/3/2018 3:33:00 PM:
In the process of property acquisition of three lots to expand park development, which is expected to be completed by the end of June. Park development and playground installation is projected for July. In addition to the playground, a walking trail, benches and lighting will be installed.

5/3/2018 3:33:00 PM:
In the process of property acquisition of three lots to expand park development, which is expected to be completed by the end of June. Park development and playground installation is projected for July. In addition to the playground, a walking trail, benches and lighting will be installed.

1/11/2018 11:36:11 AM:
Playground equipment and walking trail in process for Edgemere/Sackville neighborhood.Installation will begin once additional parcels are acquired to expand the park area.

11/13/2017 5:51:47 PM:
Purchase of playground equipment approved by City Council for new park in Edgemere/Sackville.Park will include playground,benches, game tables and walking trail.City currently seeking to acquire additional parcels to expand playground/trail.

6/28/2017 5:17:30 PM:
Finalizing concept/design.

3/31/2017 12:08:38 PM:
Scheduling meeting with neighborhood committee to assist in the selection of playground equipment in January 2017.

Last Project Update: 12/7/2020 3:54:31 PM
Fund(s): SPLOST VI - District 3 Funds | SPLOST Open Spac
Project Financial Data Last Updated On: 9/30/2020 3:07:44 PM
Appropriated Budget To Date: Expenditures To Date: Open Purchase Orders: Project Balance:
$257,720.10 $195,967.10 $0.00 $61,753.00


4/5/2019 1:21:30 PM