Project: Kensington Park Playground Project No: RE0130 Status: Complete Category: Parks And Recreation Improvements
Location: 101 Althea Ct. Start Year: 2016 End Year: 2017
Council District: 4 Project Manager: Nick Roberts NRoberts01@Savannahga.Gov
Scope: To install playground equipment and amenities in the Kensington neighborhood
Comments: 1/3/2019 4:09:45 PM:
Kensington playground development is completed.

10/5/2018 12:42:03 PM:
Kensington playground development is completed.

7/9/2018 2:34:09 PM:
Kensington playground development is completed.

4/17/2018 1:23:19 PM:
Kensington playground development is completed.

4/17/2018 1:23:19 PM:
Kensington playground development is completed.

1/16/2018 5:03:16 PM:
Current scope of project at Kennington park is completed which included playground equipment,benches,water fountain and crush gravel parking area.

11/7/2017 12:58:48 PM:
Installed Playground equipment ,benches,water fountain and crush gravel parking area.

7/26/2017 11:12:04 AM:
Remaining work on this project includes the installation of a water fountain.

3/31/2017 12:08:38 PM:
Playground equipment installed;parking lot and amenities to be completed

Last Project Update: 1/3/2019 4:09:45 PM
Fund(s): SPLOST VI - District 4 Fund
Project Financial Data Last Updated On: 1/28/2019 12:24:58 PM
Appropriated Budget To Date: Expenditures To Date: Open Purchase Orders: Project Balance:
$77,549.98 $77,549.98 $0.00 $0.00


1/16/2018 5:03:16 PM