Project: Sylvan Terrace Park Project No: RE0133 Status: Complete Category: Parks and Recreation Improvements
Location: Montgomery,Berkely Start Year: 2016 End Year: 2018
Council District: 5 Project Manager: Kelly Ledbetter| Doug Patten KLedbetter@Savannahga.Gov;DPatten@savannahga.gov
Scope: Construct a concrete trail and ADA parking in the Sylvan Terrace Neighborhood.
Comments: 12/7/2020 3:54:48 PM:
Project has been completed. The power outlet has been installed, which was the last item.

7/15/2020 1:20:26 PM:
Project has been completed. The power outlet has been installed, which was the last item.

4/7/2020 11:00:24 AM:
Project has been completed. The power outlet has been installed, which was the last item.

12/17/2019 12:56:53 PM:
The City's electrical annual contractor has installed a power outlet to the site. Once the meter is set, the power outlet will be operational.

9/20/2019 11:28:45 AM:
Construction of sidewalk and rubberized walking surface was completed in 2018. The contract to install five exercise stations around the walking trail was approved by City Council on March 28, 2019 and work was completed in May 2019. The contractor who installed the exercise equipment was Playworld Preferred and the contract amount was $47,068.00. A ribbon cutting was held in June 2019.

6/19/2019 12:14:09 PM:
Construction of sidewalk and rubberized walking surface was completed in 2018. The contract to install five exercise stations around the walking trail was approved by City Council on March 28, 2019 and work was completed in May 2019. The contractor who installed the exercise equipment was Playworld Preferred and the contract amount was $47,068.00. A ribbon cutting was held in June 2019.

4/1/2019 1:42:40 PM:
Construction of sidewalk and rubberized walking surface was completed in 2018. The contract to install five exercise stations around the walking trail was approved by City Council on March 28, 2019. The contractor is Playworld Preferred and the contract amount is $47,068.00.

1/3/2019 4:21:44 PM:
Construction of sidewalk and rubberized walking surface was completed. Additional amenities include benches, trash receptacles and lighting.

10/2/2018 2:11:45 PM:
Construction of sidewalk and rubberized walking surface was completed. Additional amenities include benches, trash receptacles and lighting.

8/2/2018 11:25:57 AM:
Construction of a rubberized walking trail was completed. Additional amenities including benches, water fountains, lighting and trash barrels will be installed by the end of the year.

5/4/2018 8:01:19 AM:
Construction of a rubberized walking trail has been completed. Amenities will be installed which include benches, water fountains, lighting and trash barrels.

5/4/2018 8:01:19 AM:
Construction of a rubberized walking trail has been completed. Amenities will be installed which include benches, water fountains, lighting and trash barrels.

1/16/2018 5:06:04 PM:
A rubberized walking trail is being added to sidewalk at Sylvan Park; once trail is completed, amenites will include lighting, water fountains and benches.

11/7/2017 12:45:52 PM:
Fencing, bollards ,sidewalk and ADA parking completed. Contract modification request in process for approval to construct rubberized walking trail along the sidewalk.

7/24/2017 4:02:26 PM:
Side walk has been installed; Remaining work to complete park amenities includes installation of: two water fountains, concrete walks to connect walking trail, security lighting, irrigation system, rubberized walking trail, etc.

3/31/2017 12:08:38 PM:
Fence and bolloards installed,walking trail construction expected to start within 60 days

Last Project Update: 12/7/2020 3:54:50 PM
Fund(s): SPLOST VI - District 5 Fund
Project Financial Data Last Updated On: 9/30/2020 3:07:44 PM
Appropriated Budget To Date: Expenditures To Date: Open Purchase Orders: Project Balance:
$305,275.78 $305,275.78 $0.00 $0.00


4/1/2019 1:42:40 PM