Capital Improvement Program

Project: Twickenham Greenspace Project No: RE0222 Status: To Be Closed Category: Parks and Recreation Improvements
Location: Goebel Ave at Beech St Start Year: 2017 End Year: 2021
Council District: 3 Project Manager: Byron Stiles BStiles@Savannahga.Gov
Scope: Enhancements to Twickenham Greenspace will include a walking trail, benches, trash cans, lighting and ornamental plantings.
Comments: 7/5/2023 2:12:26 PM:
Park has been completed and turned over to Park and Tree.

12/1/2021 11:09:41 AM:
Park has been completed and turned over to Greenscapes.

8/31/2021 12:31:48 PM:
Park has been completed and turned over to Greenscapes.

4/12/2021 9:13:58 AM:
Park has been completed and turned over to Greenscapes.

12/10/2020 12:54:37 PM:
Change order to correct storm water issues has been completed. Jogging trail, lighting, benched, receptacle, bollards have been installed. Close out process has begun.

10/5/2020 2:39:09 PM:
During the 2nd quarter of 2020 stormwater work has continued begun and the jogging trail is 80% complete. Project is expected to be completed by 9/20.

6/26/2020 1:11:02 PM:
Project has been brought into budget after value engineering process. Construction is currently on the 4/9/20 agenda for approval.

12/9/2019 2:35:20 PM:
After last batch of value engineering, the project is still over budget. CIP team has reopened value engineering to get project within budget.

11/12/2019 12:16:53 PM:
Wolverton engineering has completed site plans and Johnson-Laux will be used as the contractor through Gordian using the state contract. Currently working on some value engineering items to insure project is within budget, specifically decreasing the piling depth for the walking bridges. Once we receive proposal from Johnson-Laux, project will be placed on council for approval.

7/9/2019 11:24:10 PM:
Site survey work has been completed. Staff is working with our contract engineer on design details and preparation of construction drawings for review and approval.

4/5/2019 5:31:23 PM:
Site survey work has been completed. Staff is working with our contract engineer on design details and preparation of construction drawings for review and approval.

1/11/2019 5:05:30 PM:
New project. Staff is working with our contract engineer on design details and preparation of construction drawings for review and approval.

11/14/2018 9:05:27 AM:
CIP RE0222 was previously Holly Heights Greenspace. On September 13, 2018 City Council approved Amendment #6 which included Holly Heights Greenspace funding to be used to establish a Twickenham Greenspace capital account, resulting in RE0222 changing to Twickenham Greenspace. To date, staff prepared conceptual plans for the Twickenham Greenspace to include a walking trail, bridges, benches, trash cans, lighting, ornamental plantings and a dog park.

7/6/2018 11:55:11 AM:
The Holly Heights Master Plan was revised by relocating many elements to non-FEMA lots and removing the Community Center. The design phase is anticipated to commence July 2018 with construction starting by December 2018.

6/12/2018 11:33:39 AM:
A conceptual plan for park development includes a playground, shelter, community garden, basketball court and community center. Costs and concept options are being investigated and evaluated. Completion of initial design documents is expected in July.

6/12/2018 11:33:39 AM:
A conceptual plan for park development includes a playground, shelter, community garden, basketball court and community center. Costs and concept options are being investigated and evaluated. Completion of initial design documents is expected in July.

1/12/2018 3:05:55 PM:
Conceptual plan for park development has been done.The park would include playground,pavillion,basketball courts,community garden and community center.

11/15/2017 4:44:56 PM:
Conceptual master plan is being finalized to develop park to serve the needs of neighborhood.

6/28/2017 5:20:19 PM:
Currently in conceptual/design phase.

3/31/2017 12:08:38 PM:
Developing scope of work for master plan

Last Project Update: 7/5/2023 2:12:55 PM
Fund(s): SPLOST VI - District 3 Fund
Project Financial Data Last Updated On: 11/30/2023 12:00:00 AM
Appropriated Budget To Date: Expenditures To Date: Open Purchase Orders: Project Balance:
$290,096.91 $290,096.91 $0.00 $0.00


7/6/2018 11:55:11 AM