Project: Summerside Playground Project No: RE0223 Status: Complete Category: Parks and Recreation Improvements
Location: Clinch Street Start Year: 2016 End Year: 2019
Council District: 5 Project Manager: Doug Patten| Kelly Ledbetter KLedbetter@Savannahga.Gov;DPatten@savannahga.gov
Scope: To replace an aging playground equipment in the Summerside Neighborhood
Comments: 8/28/2023 11:51:50 AM:
Project was completed in August 2020.

3/25/2021 9:52:43 AM:
Project was completed in August 2020.

12/7/2020 3:55:46 PM:
Project was completed in August 2020.

10/5/2020 2:40:19 PM:
During the 2nd quarter of 2020 the benches were installed and the sign was adjusted to be parallel with Clinch Street. The project is expected to be complete in July 2020.

3/16/2020 9:43:30 AM:
The sitework is complete and the playground has been installed. A change order is needed to install two benches move the sign to be parallel with Clinch Street.

12/17/2019 12:59:57 PM:
The sitework is currently under construction. A change order was needed to replace poor soils that were encountered on the site. The sitework is expected to be completed no later than the early 1st Quarter of 2020. Once the sitework is complete the playground installer will be able to install the playground.

9/20/2019 11:30:44 AM:
Pricing for Phase I of the project was received and is expected to go before City Council in early fall of 2019. Phase I will include installing the new playground, constructing the parking lot, and installing the park sign. Construction is expected to begin by mid fall 2019.

7/3/2019 11:50:48 AM:
Design work is complete. Pricing for the park was received and is currently under review.

4/1/2019 1:45:11 PM:
Survey for Summerside Park has been completed and the project is currently under design. The park will include a playground, a shelter, picnic tables and benches. The design is expected to go to permitting in April 2019.

1/3/2019 4:30:13 PM:
Survey for Summerside Park has been completed and the design plan is currently under review. The park will include playground, shelter, picnic tables and benches.

10/3/2018 5:33:11 PM:
Survey for Summerside Park has been completed and the design plan is currently under review. The park will include playground, shelter, picnic tables and benches.

7/3/2018 9:24:50 AM:
Site clearing is completed and topographic survey is being schedule for site. After survey has been completed, a site plan showing the final layout and grading plan and a conceptual design will be developed.

4/6/2018 3:16:15 PM:
Bids received to proceed with site clearing. After site is cleared, design process will begin to include shelter, playground and park amenities.

4/6/2018 3:16:15 PM:
Bids received to proceed with site clearing. After site is cleared, design process will begin to include shelter, playground and park amenities.

1/12/2018 3:08:24 PM:
Site clearing is expected to be completed in the first quarter of 2018. Park development will include playground,shelter,picnic tables,benches and water fountain.

11/15/2017 4:25:10 PM:
Additional funds will be needed to develop park at expanded location.

6/30/2017 2:57:30 PM:
Currently considering location of playground

3/31/2017 12:08:38 PM:
Currently considering location of playground

Last Project Update: 12/7/2020 3:56:05 PM
Fund(s): SPLOST VI - District 5 Fund
Project Financial Data Last Updated On: 9/30/2020 3:07:44 PM
Appropriated Budget To Date: Expenditures To Date: Open Purchase Orders: Project Balance:
$345,098.08 $328,252.25 $0.00 $16,845.83