Location:
Barnard St and West 53rd St |
Start Year:
2016 |
End Year:
2017 |
Council District:
5 |
Project Manager:
Gordon Denney |
GDenney@Savannahga.Gov |
Scope:
Improvements at Ambush Park to include an irrigation system, new lighting, replacement of seating/trash receptacles, and landscaping. |
Comments:
|
1/11/2019 5:05:45 PM: Work completed. CIP being closed out.
10/5/2018 5:39:30 PM: Work completed. CIP being closed out.
7/9/2018 2:35:17 PM: Georgia Power has completed installation of new decorative lighting. All work completed. Project can be closed
4/6/2018 1:17:11 PM: The electrical conduit has been installed and we are currently awaiting Georgia Power to complete installation of new decorative lighting.
4/6/2018 1:17:11 PM: The electrical conduit has been installed and we are currently awaiting Georgia Power to complete installation of new decorative lighting.
12/29/2017 2:07:19 PM: Georgia Power provided us with a lighting plan and agreement which we reviewed and submitted for execution. We are currently waiting for Georgia Power to schedule installation of the new decorative lights along the walkways.
10/6/2017 1:24:09 PM: Met with Georgia Power and are awaiting a lighting plan for review. Once approved and an agreement executed with the City they will install the new decorative lights along the walkways.
6/30/2017 3:10:57 PM: Installed new automated irrigation system, picnic table, bench and landscaping.
3/31/2017 12:08:38 PM: Working on Lighting Plan
|
Last Project Update:
1/11/2019 5:05:45 PM |
Fund(s):
SPLOST VI - District 5 Fund |
Project Financial Data Last Updated On:
1/28/2019 12:24:59 PM |
Appropriated Budget To Date:
|
Expenditures To Date:
|
Open Purchase Orders:
|
Project Balance:
|
$37,232.73 |
$37,232.73 |
$0.00 |
$0.00 |
|

12/29/2017 2:07:19 PM
|