Tide To Town, Savannah’s Urban Trail System, will be a protected network of walking and bicycling trails connecting all of Savannah’s neighborhoods, from the heart of the city to our marshes and waterways. Tide To Town will serve every aldermanic district within the City of Savannah. |
| Comments:
|
6/13/2025 9:05:05 AM: Middleground Road design is underway. Survey field work is complete and the database is underway. Early coordination letters are being submitted and reviewed by GDOT. Archaeology and ecology field work is underway. A proposal for full design services was submitted for Montgomery Cross Road. The Access Management Memo was submitted to the City for review.
1/31/2025 10:20:53 AM: Middleground Road was awarded to Kimley-Horn and Notice to Proceed for design was issued on 12/27/2024. Montgomery Cross Road is in the conceptual design phase and a traffic engineering report was completed by CHA.
6/17/2024 8:19:57 AM: Design RFQ for Middleground Road has been advertised and staff is currently in negotiations with the top scoring consultant.
12/12/2023 8:47:00 AM: Design RFP for Middleground Road is complete and awaiting GDOT approval to advertise.
7/5/2023 2:29:45 PM: Design RFP for Middleground Road is complete and awaiting GDOT approval to advertise.
|
| Last Project Update:
6/13/2025 9:35:56 AM |
| Fund(s):
Contrbtn Frm Generl Fn |
| Project Financial Data Last Updated On:
5/31/2025 12:00:00 AM |
| Appropriated Budget To Date:
|
Expenditures To Date:
|
Open Purchase Orders:
|
Project Balance:
|
|
$473,768.51 |
$261,811.57 |
$190,165.25 |
$21,791.69 |
|